Mississippi State University 2006
From 2006.igem.org
(Difference between revisions)
Line 87: | Line 87: | ||
<h3>Accomplishments</h3> | <h3>Accomplishments</h3> | ||
+ | * October 25- Gather results from final tests and analyze. | ||
+ | * October 24- Took pictures of vials for final tetsing. | ||
+ | * October 23- Performed gassing for final testing (Solid Media). | ||
+ | * October 22- Inoculation of E.coli + plasmid into solid media. | ||
+ | * October 17- Sent two constructions to the registry, and registered our parts on the website. | ||
+ | * October 5- Analyzed results of second test. | ||
+ | * October 4- Took pictures of vials for second testing. | ||
+ | * October 3- Performed gassing for second testing (Liquid Media). | ||
+ | * October 2- Inoculation of E.coli + plasmid into liquid media. | ||
+ | * September 29- Built testing station to be used with spectrometer. | ||
+ | * September 22- Analyzed results of first test. | ||
+ | * September 21- Took pictures of vials in first test. | ||
+ | * September 20- Performed gassing of first test (Solid Media). | ||
+ | * September 18- Inoculation of E.coli + plasmid into solid media. | ||
+ | * September 12-14- Gathered resources to begin testing. | ||
+ | * August 29-September 8- Searched for the instrumentation needed to do the testing. | ||
+ | * August 24- Digested plasmids to test the ligation of HybB (successful). | ||
+ | * August 22- Sequenced promoter for verification | ||
* August 18- Group meeting with faculty, Publicity and preparation for Jamboree discussed. | * August 18- Group meeting with faculty, Publicity and preparation for Jamboree discussed. | ||
* August 16- Planning for Jamboree with help from James. | * August 16- Planning for Jamboree with help from James. |
Revision as of 16:03, 26 October 2006
The TeamFaculty Members:
Students:
|
Introduction
|
H2 Reporter
|
Results |
Discussion |
Accomplishments
|