Lab work started on June 8.
+
Lab work started on June 7.
-
First weeks: primer designs, vector minipreps, transformations, PCRs & control digestions.
+
June - July: primer designs, vector minipreps, transformations, PCRs & control digestions.
 +
 
 +
Late July: each team member was assigned a list of constructs and deadlines for their completion.
 +
 
 +
August: first constructs are due August 15.
[http://2006.igem.org/University_of_Ljubljana_%26_National_Institute_of_Chemistry%2C_Ljubljana%2C_Slovenia_2006 Back home]
[http://2006.igem.org/University_of_Ljubljana_%26_National_Institute_of_Chemistry%2C_Ljubljana%2C_Slovenia_2006 Back home]

Revision as of 14:38, 1 August 2006

We will report here about problems and successes in our lab work. Don't expect this to be really up to date, but we'll try to give some insight into how we proceed.

___________

Lab work started on June 7.

June - July: primer designs, vector minipreps, transformations, PCRs & control digestions.

Late July: each team member was assigned a list of constructs and deadlines for their completion.

August: first constructs are due August 15.